Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list?
Your organization has been awarded a new contract based on which you are allowed to sell:
Items not tracked in inventory Inventory items Services

Which contract structure would fulfill your requirement of item sales?
You configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To-
Customer and Contract and Contract Line dimensions.
Identify the reason for this behavior.
You recently made some changes to a project contract and the current status of the contract is Under Amendment.
Identify the correct sequence of activities that can take place on that contract.
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B for contract Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y -
Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario.
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost.
In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement?
Your customer wants a project start date to cascade to the project tasks, bust does not want the finish date to be cascade.
Identify the default setup in a project template that can be used to enable this.
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit.
Why is the project accountant unable to see the transactions for the China business unit?
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.
Identify the reason for this problem.
You are implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-charge transactions happen between business units within the same legal entity. Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement.