Question 1
Multiple choice

Select the three statements that are true about the Project management Plan.

A.

It is created in the Manage Project Execution and Control phase.

B.

It is the single most important work product produced by the project manager.

C.

Its main focus is on scheduling the project.

D.

It is created by the project manager and the client.

E.

It is a conceptual work product comprised of process components detailing the tools and/or approach for each OUM Manage process.

F.

It provides a framework for the Analysis and Design processes.

Question 2
Multiple choice

Select the three constraints that are missing in this Triple Constraint triangle.

A.

Usability

B.

Scope

C.

Cost

D.

Complexity

E.

Product

F.

Schedule

Question 3
Multiple choice

Which two statements are true about the Change Control Board (CCB)?

A.

It meets daily during Project Execution and Control.

B.

It is an internal project organization that is responsible for reviewing and resolving change requests.

C.

It is a person, group, or business that has a shared interest in a particular set of activities.

D.

It escalates changes affecting scope to the steering committee.

Question 4
Multiple choice

Which identifies the quality standards that are relevant to the project and how to satisfy them?

A.

Quality Assurance

B.

Quality Control

C.

Quality Planning

D.

Process Improvement

Question 5
Multiple choice

Select two objectives of the OUM Implement Elaboration phase.

A.

Confirm the project scope.

B.

Identify and validate the architecturally significant requirements.

C.

Identify key configuration decisions.

D.

Prepare the system for acceptance test and deployment.

E.

Address critical operational issues.

F.

Obtain acceptance.

Question 6
Multiple choice

Select two objectives of the OUM Manage Project Execution and Control phase.

A.

Manage the project resources to deliver on time and in budget.

B.

Gain project acceptance.

C.

Release staff.

D.

Execute against the Project Management Plan.

Question 7
Multiple choice

Which three risks does Organizational Change Management seek to mitigate?

A.

Employee attrition

B.

Vendor delivery rates

C.

Lack of personal effectiveness

D.

Interruptions to the business

E.

Natural disasters

Question 8
Single choice

In which process does the Review and Analyze Bid Materials drive the Validated Scope in the Scope Management process?

A.

Financial Management

B.

Infrastructure Management

C.

Organizational Change Management

D.

Bid Transition

Question 9
Single choice

What is the purpose of the Project Execution and Control Phase?

A.

To prove the solution described in the scope document meets the project requirements.

B.

To provide adequate visibility into actual progress so that management can take effective actions when necessary.

C.

To successfully transition from the sales team to the delivery team.

D.

To provide an adequate foundation for the Project Management Plan.

Question 10
Single choice

Which is true about OUM Manage?

A.

It emphasizes clearly documenting the scope of the project and the exact procedures to implement changes to this scope.

B.

It is not possible to control the project timeline without a detailed project plan.

C.

It is necessary to only document the items in the scope.

D.

If the project sponsor requires a functional change, the project team must comply with the request.

Showing 10 of 98 questions · Unlock the full set