Q1 Multiple choice

A one-time additional public holiday has been announced for this year. You update the PA Calendar, which is used for Resourcing with this exception. Select the two options required to ensure that this change is reflected in the existing assignment on resource calendars.

Select all that apply.

  • A

    Run"PRC: Generate CalendarSchedules."

  • B

    Run "PRC: Rebuild Resource Timeline."

  • C

    Inform Resource Managers that they will have to redo all the existing planning.

  • D

    Run "PRC: AutomatedCandidate Search."

  • E

    Run "PRC:Refresh project summary amounts."