Question 1
Single choice

You are a portfolio manager, and a filter has been set to identity and assign projects to your portfolio.
You are in Primavera P6 EPPM web interface.

How could you be certain that the list of projects in your portfolio is complete?

A.

By manually hiding projects

B.

By manually adding new projects

C.

By manually refreshing the filter

D.

By manually updating projects

Question 2
Single choice

A Physical % complete activity has an original duration of 10, and a remaining duration of 10. The actual start is assigned to the activity. Physical % is updated to equal 80%.

What is the remaining duration for this activity?

A.

80

B.

10

C.

2

D.

8

Question 3
Multiple choice

Select two true statements about the Portfolio Analysis tab in Primavera P6 EPPM.

A.

Conducts a side-by-side comparison of an unlimited number of portfolios

B.

Conducts a side-by-side comparison of two projects

C.

Conducts a side-by-side comparison of two portfolios

D.

Conducts a side by-side comparison of one project displayed in different views

E.

Conducts a side by-side comparison of the same portfolio displayed in different views

Question 4
Multiple choice

Identify two formats available in the Capacity Planning chart.

A.

Stacked histogram

B.

Pie

C.

Area

D.

Variance

E.

Cost

Question 5
Single choice

You are working with a customer that has had Primavera P6 running in a global instance for four years the customer has asked you to come in and review the instance to identity opportunities for optimizing the system. As you look into the coding libraries, you see much duplication of project codes. You recommend that the customer come to consensus on the duplicate codes and values, and then eliminate the redundant codes.

What functionality should you utilize to minimize the potential disruption to the user base?

A.

Send out communication that the codes will be eliminated.

B.

Eliminate the codes and manage usage issues by exception.

C.

Document, usage of each code and value in filters and views.

D.

Merge the codes rather than eliminating them.

Question 6
Single choice

Identify the true statement regarding Activity Step templates.

A.

Activity % complete must be Physical when using Activity Step templates.

B.

There are limits to the number of Activity Step templates in the database.

C.

Activity Step templates are the place where resources are allocated and assigned.

D.

Activity Step Templates are governed by global security.

Question 7
Multiple choice

The Open Requests for Resource's portlet lists unstaffed assignments involving roles on the selected role team. Identify two ways that the portlet display can be organized.

A.

Role by Project

B.

Role by Resource

C.

Project by Role

D.

Resource by Project

E.

Resource by Role

Question 8
Single choice

Identify one filter enhancement in P6 R8.

A.

Apply multiple filters simultaneously

B.

Create filters with no more than three criteria

C.

Cut, Copy, and paste filters

D.

Assign filters to unique, single activity views

Question 9
Single choice

Identify this window.

A.

Portfolio

B.

Portfolio view

C.

Dashboard

D.

Project statistics

Question 10
Single choice

Select the true statement regarding currencies.

A.

Only one base currency is supported per database.

B.

Currencies are updated daily per exchange rates.

C.

Only 10 currencies are supported in Primavera.

D.

Only two currencies are supported in Primavera.