Exit demo 210-010 VCE Vblock Systems Deployment and Implementation - Core PDF format · free preview

VCE 210-010 - Questions & Answers

Free preview · every answer includes a full explanation

Product page: https://prepkeys.com/210-010.html

Question 1
Single choice

When powering on a Vblock System what is the correct power up sequence?

A.

Switches, AMP, SAN, UCS chassis, and UCS blades

B.

Switches, SAN, UCS chassis, UCS blades, and AMP

C.

Switches, AMP, UCS chassis, UCS blades, and SAN

D.

Switches, SAN, AMP, UCS chassis, and UCS blades

Question 2
Multiple choice

What are three primary site survey considerations? (Choose three.)

A.

Site information

B.

Technical resources

C.

Customer power requirements

D.

Data center physical audit

E.

Disaster recovery plan

Question 3
Single choice

Which EMC software is required to initialize a Vblock System 200 storage array?

A.

Unisphere Service Manager

B.

Unisphere Server Utility

C.

VNX Installation Assistant

D.

Unisphere Client

Question 4
Single choice

Which EMC software is required to upgrade code on a Vblock System 200 storage array?

A.

Unisphere Service Manager

B.

Unisphere Server Utility

C.

VNX Installation Assistant

D.

Unisphere Client

Question 5
Multiple choice

Which two statements are correct about Vblock System Release Certification Matrix (RCM) upgrades? (Choose two.)

A.

The RCM must be applied by VCE certified resources.

B.

When upgrading to a new RCM, all components may not require an upgrade.

C.

The most recent RCM version must be applied.

D.

An addendum to the RCM may be issued to address a bug or software issue.

Question 6
Single choice

Which Cisco Catalyst switch is used for network management on a Vblock System 200?

A.

Cisco Catalyst 2960

B.

Cisco Catalyst 3560

C.

Cisco Catalyst 3750

D.

Cisco Catalyst 4500

Question 7
Single choice

In addition to the Logical Configuration Survey (LCS), which document is required prior to manufacturing a Vblock System 720?

A.

Configuration Reference Guide

B.

VCE change control form

C.

VCE Vblock Systems Release Certification Matrix

D.

EMC bin file request form

Question 8
Single choice

For bare metal deployments, which statement ensures VCE is able to provide reasonable-effort support?

A.

The ratio of bare metal to virtualized hosts cannot be more than 40 percent.

B.

A minimum of five virtualized hosts must be enabled.

C.

Bare metal workloads are run on separate physical spindles, disk groups, and pools.

D.

Systems cannot include hypervisor technologies other than VMware.

Question 9
Multiple choice

Customers provide the information used to develop the Logical Configuration Survey (LCS) before manufacturing begins.

What information is required? (Choose two.)

A.

syslog server IP address

B.

NTP server IP address

C.

method of device access (telnet or SSH)

D.

MIB browser IP address

Question 10
Multiple choice

The implementation profile located in the Logical Configuration Survey (LCS) identifies if the customer will be using which two solutions? (Choose two.)

A.

EMC SnapView

B.

Cisco IAC

C.

Cisco Unified Communications

D.

VMware vCloud Director