Your company has had several large projects fail due to cost overruns and the lack of available resources.
These projects use an enterprise project type named Large IT Project and use a workflow to govern the
approval of the projects. The workflow consists of four phases; Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.
You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
All work and progress on individual projects must be reflected in the e-commerce portal development program.
Each group must be able to manage their own tasks.
You need to set up the e-commerce portal development program and its associated projects in Microsoft
PPM.
Where should you add resources?
You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost, Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should you use? Each correct answer presents part of the solution.
You are project manager for an organization that is uses Microsoft PPM. You need to create a project deliverable for the current project.
What should you do?
You are a project manager using Microsoft PPM,
You need to create a new project that uses one of your company's templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.
This question requires that you evaluate the underlined text to determine if it is correct.
To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.
Review the underlined text If it makes the statement correct select "No change is needed." If the statement is incorrect select the answer choice that makes the statement correct
This question requires that you evaluate the underlined text to determine if It is correct.
Cost resources affect the schedule when they're assigned to tasks.
Review the underlined text. If it makes the statement correct select "No change is needed.- If the statement is incorrect, select the answer choice that makes the statement correct
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
You are an administrator for an organization that uses Microsoft PPM. A project manager is building a team for a project. The project manager reports that a newly hired resource is not visible in Build Team.
You need to ensure that newly added users are available in Build Team.
What should you do?
You are a project manager for an organization that is using Microsoft Project.
You have enabled Single Entry Mode and team members update their task status using timesheets.
You need to see how these updates impact your project before you approve the tasks.
What should you do?