Exit demo AD0-E908 Adobe Workfront Core Developer Professional PDF format · free preview

Adobe AD0-E908 - Questions & Answers

Free preview · every answer includes a full explanation

Product page: https://prepkeys.com/ad0-e908.html

Question 1
Multiple choice

A Workfront system administrator is creating a new layout template for a group of users.

What two items can be customized here? (Choose two.)

A.

Views, filters, and groupings used with reports

B.

On-screen terminology

C.

User attributes including schedule, group, and job role

D.

What notifications the user can receive

Question 2
Multiple choice

Which two actions are necessary for a request queue to be visible in the system? (Choose two.)

A.

Check the box to publish as a help request queue

B.

Add a routing rule to the queue details

C.

Indicate the default fields to be shown on all requests

D.

Ensure that the queue project is within a status that equates to Current

Question 3
Multiple choice

The creative services team often completes continuing education courses or specific certifications to expand their skillset. These hours are not linked to a specific project. They have asked the system administrator to create an hour type that will appear on their timesheet.

What are two steps the system administrator would take to create a new hour type named Training and Certifications? (Choose two.)

A.

Set the hour type as "General*

B.

Associate the hour type with the creative services team

C.

Create a non-billable project to capture logged time

D.

Uncheck the box "Count as Revenue"

Question 4
Single choice

A system administrator is asked to share a financial report with internal users in the system. The system also has external vendors within it who should not see the financial report.

What should the system admin do?

A.

Check the "Share System-wide" checkbox on the report with limitations to the primary company.

B.

Give view access to the report to the people within the primary company in Adobe Workfront

C.

Check the "Share System-wide" checkbox on the report and remove the external users

Question 5
Multiple choice

A project manager would like to have consistent project data fields to be used in the project reports they create. Which two options would address that need9 (Choose two.)

A.

Custom fields within the Custom Form can be pre-populated with data.

B.

Custom fields can dictate consistent project dashboards.

C.

Custom Forms can identify the best available resource for a specific role within a project.

D.

The Custom Form is attached to the template used for the project creation.

Question 6
Multiple choice

To which two objects in Workfront can a dashboard be added in the left navigation? (Choose two.)

A.

Portfolio

B.

Timesheet

C.

Project

D.

Calendar

Question 7
Single choice

Where in the standard report builder can a person use a Wildcard?

A.

Filter

B.

Chart

C.

Grouping

Question 8
Multiple choice

Which two objects can an issue be converted to? (Choose two.)

A.

Task

B.

Update

C.

Project

D.

Request

Question 9
Single choice

A client wants to keep track of project metrics based on the request that was submitted, but they do not want the requestor to fill this information out.

How would a system administrator configure this request?

A.

Create a section break to the request Custom Form containing the metric fields, and change the permissions so it is not visible to the requestor

B.

Restrict access to the metric fields by removing request queue access from the requester and change their access level to "view"

C.

Do not make the additional fields in the Custom Form available to the requester, but add them to the project details section

Question 10
Single choice

What does the Cost Performance Index (CPI)of a project in Workfront track?

A.

Relationship between the planned and actual cost

B.

Difference between the planned benefit and budgeted cost

C.

Total expected value after calculating its benefit and removing the costs

Showing 10 of 70 questions · Unlock the full set