Question 1
Single choice

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

A.

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

B.

Project Manager's relative effort estimate that will be needed to implement and test the user ^ story

C.

Detailed bottom-up effort estimate by the product owner that breaks up each story into short ^ tasks

D.

Relative effort estimate in Ideal Person Days that reflects the best estimate by the project ^ team

Question 2
Single choice

You are implementing SAP S/4HANA Cloud, public edition for your customer.

How are your customer systems activated?

A.

Via the SAP Cloud ALM

B.

Via the SAP Contact Center

C.

Via the Central Business Configuration System

D.

Via the SAP Business Technology Platform

Question 3
Single choice

Which functionality is available in Focused Build?

A.

User Experience Monitoring

B.

Test Management

C.

Integration Monitoring

D.

Custom Code Management

Question 4
Single choice

What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?

A.

SAP Support Portal

B.

SAP Roadmap Viewer

C.

SAP Transformation Navigator

D.

SAP Cloud ALM

Question 5
Single choice

Which of the following is the customer's responsibility in both on-premise and private cloud scenarios?

A.

Database

B.

Middleware

C.

Operating system

D.

Servers

Question 6
Single choice

When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape, in which phase are the Business Roles updated?

A.

Explore

B.

Realize

C.

Deploy

D.

Discover

Question 7
Single choice

When deploying a new implementation on-premise, which of the following is recommended when performing custom development?

A.

SAP Business Technology Platform

B.

SAP Best Practices

C.

SAP API Business Hub

D.

SAP ABAP Workbench

Question 8
Single choice

Which of the following is a key characteristic of the Agile project approach?

A.

Frequent quality gates

B.

Frequent and detailed project scheduling

C.

Formal and detailed documentation

D.

Iterative build with frequent inspections

Question 9
Single choice

What criterion does the product owner use to sequence the product backlog?

A.

Business priority

B.

Resource availability

C.

Relative effort

D.

Complexity

Question 10
Single choice

What is the purpose of the scrum board?

A.

To visualize team progress

B.

To manage the resource load

C.

To show the functional breakdown of the solution scope

D.

To document the results of the Integration Test

Showing 10 of 82 questions · Unlock the full set