Exit C_ACTIVATE05 SAP Certified Associate - SAP Activate Project Manager
Question 1 of 5
0% complete
Q1 Multiple choice

Which of the following tasks are part of the Production support after the Go Live key deliverable? There are 2 correct answers to this question.
Response:

Select all that apply.

  • A

    Resolve issues identified during the Hyper Care period

  • B

    Provide further training to customer end users

  • C

    Set up the Operations Control Center

  • D

    Perform a Technical systems test

Previous Next