Question 1
Single choice

What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of
SAP Activate?
Please choose the correct answer. Response:

A.

Project Charter

B.

Project Documentation

C.

Knowledge transfer to end users

D.

Learning plan

Question 2
Single choice

Which tool can you use to collaborate with other SAP Activate methodology practitioners? Please choose the correct answer.
Response:

A.

SAP Jam

B.

SAP Solution Manager

C.

SAP Implementation Assistant

D.

Roadmap Viewer

Question 3
Single choice

What is the final activity in the Realize phase of a new implementation of SAP S/4HANA cloud edition?
Please choose the correct answer.
Response:

A.

Data migration

B.

End-to-End walkthrough

C.

Readiness check

D.

Solution validation

Question 4
Multiple choice

Which tools does SAP Activate provide to support Guided Configuration? There are 3 correct answers to this question.
Response:

A.

Solution Builder

B.

Expert Configuration

C.

Self Service Configuration

D.

SAP Solution Composer

E.

Model Company

Question 5
Single choice

What does SAP Activate recommend to keep team members informed and aligned? Please choose the correct answer.
Response:

A.

Daily status meeting with project manager

B.

Daily team stand-up meeting

C.

Daily e-mail status updates to project manager

D.

Daily progress review meeting with sponsor

Question 6
Single choice

How can SRCUM teams be organized?
Please choose the correct answer.
Response:

A.

By job title

B.

By work stream

C.

By project phase

D.

By project governance level

Question 7
Single choice

What is the minimum number of quality gates mandated by the SAP Activate methodology? Please choose the correct answer.
Response:

A.

0

B.

3

C.

4

D.

5

Question 8
Multiple choice

Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition?
There are 2 correct answers to this question. Response:

A.

Solution Activation

B.

Optimize software Change Control Management

C.

Training delivery

D.

Access organizational and production readiness

Question 9
Single choice

Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the correct answer.
Response:

A.

Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks

B.

Relative estimate in ideal person days that reflects the best estimate provided by the project team

C.

Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity

D.

Product Owner's relative estimate of the effort that will be needed to implement the user story

Question 10
Multiple choice

Which activities are critical for delivering Agile projects? There are 2 correct answers to this question.
Response:

A.

Retrospective agenda creation

B.

Sprint planning

C.

Release planning

D.

Blueprint scheduling