Question 1
Single choice

What happens if the appended indicator is not set and an order is appended? Please choose the correct answer.
Response:

A.

Order planned value is not added to the WBS planned value

B.

Order planned value is deducted from the WBS planned value

C.

Order planned value increases the WBS element planned value

D.

Order planned value is multiplied to the WBS element planned value

Question 2
Single choice

Which function allows you to check consistency of the dates within the project structure with or without taking activities into account? Please choose the correct answer.
Response:

A.

Sets of dates

B.

Check dates

C.

Planning methods

D.

Extrapolate

Question 3
Multiple choice

In which of the following levels can you execute BOM transfer in the order browser? There are 3 correct answers to this question.
Response:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

Question 4
Single choice

How do you evaluate and display details of orders and networks that create capacityrequirements at the work centers?
Please choose the correct answer.
Response:

A.

Standard overview

B.

Capacity detail list

C.

Variable overview

D.

Tabular overview

Question 5
Single choice

Can the user status forbid business transactions that the system status allows? Please choose the correct answer.
Response:

A.

No, user status can only create a warning.

B.

Yes, by creating an appropriate status profile.

C.

Yes, if the status number of the user status is defined with higher priority.

D.

No, system status has a higher priority than user status.

Question 6
Single choice

Which types of networks store all the activity and material component costs at the network header level and behave in the same way as all other order categories? Please choose the correct answer.
Response:

A.

Order header networks

B.

Order category networks

C.

Assignment networks

D.

Header assigned networks

Question 7
Multiple choice

What is copied when transferring a simulation version back to an operative project? There are 3 correct answers to this question.
Response:

A.

Plan costs

B.

WBS elements

C.

Actual work

D.

Maintenance orders assigned to the project

E.

Network activities

Question 8
Multiple choice

What are the different views available for capacity planning and work center planning? There are 2 correct answers to this question.
Response:

A.

Work center view

B.

Capacity planning view

C.

Periodic view

D.

Project view

Question 9
Multiple choice

Which statements about project coding mask are true?
There are 3 correct answers to this question.
Response:

A.

You must always use a project coding mask for your projects.

B.

The project coding mask can begin with a numerical key.

C.

The project coding mask can be shortened later, even if projects have already been created with this project coding mask.

D.

In project number maintenance, special characters are automatically determined using the project coding mask.

E.

You can lock a project coding mask for standard projects or operative projects.

Question 10
Single choice

An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them? Please choose the correct answer.
Response:

A.

Activity analysis tool

B.

Relationship analysis tool

C.

Cycle analysis tool

D.

Loop analysis tool