Question 1
Single choice

Which is a purpose of using a risk maturity model?

A.

Identify where the application of risk management within an organization can be improved

B.

Understand the nature of risks facing an organization and the actions needed to respond

C.

Provide independent risk information at key decision points within a programme or project

D.

Show to which organizational activities risk management should be applied

Question 2
Single choice

Which does the SWOT analysis technique help to identify about an organization?

A.

Long-term trends

B.

Stakeholder views

C.

Corporate governance requirements

D.

Internal strengths

Question 3
Single choice

Which technique can be used to clarify potential sources of risks across an activity?

A.

Probabilistic risk models

B.

Summary risk profiles

C.

Risk breakdown structure

D.

Decision trees

Question 4
Single choice

What objectives are associated with decisions on risks to the achievement of long-term goals?

A.

Strategic

B.

Programme

C.

Project

D.

Operational

Question 5
Single choice

Which explains a use of the risk management policy in the identify context' step?

A.

Identifies changes to the organization's market

B.

Identifies how past events could become sources of risk

C.

Describes how corporate governance will affect the risk management process

D.

Understand the maximum amount of risk that should be taken

Question 6
Single choice

What step is used to determine those risks which have the greatest effect on the objectives of a planned activity?

A.

Identify

B.

Assess

C.

Plan

D.

Implement

Question 7
Single choice

Which is NOT a reason for carrying out an `M_o_R health check?

A.

Identify areas for improvement

B.

Help gain maximum value from investment in risk management

C.

Provide a snapshot of the current status of identified risks

D.

Review how well risk management practices have been embedded

Question 8
Single choice

Which is NOT an action needed to achieve the goal of the 'assess - evaluate' step?

A.

Determine which other risks will occur if a risk occurs

B.

Calculate the total risk exposure for the activity

C.

Evaluate the effectiveness of risk management across the organization

D.

Determine which risks are independent of other risks

Question 9
Single choice

Which role provides sponsorship to ensure that risk management is embraced within the organization?

A.

Senior manager

B.

Manager

C.

Assurance

D.

Risk specialist

Question 10
Single choice

What step is used to determine the time period when a risk might occur?

A.

Identify - risks

B.

Assess - estimate

C.

Assess - evaluate

D.

Identify context