Q1 Single choice

A group of activities within Release Management is roll-out, distribution and installation.

What should be ensured as part of these activities?

  • A

    Changes are scheduled based upon priority and risk.

  • B

    Contingency and back-out plans are available.

  • C

    Redundant products, services and licenses are decommissioned.

  • D

    The Release is tested to the satisfaction of the Customers.