Which of the following are outputs of the Direct and Manage Project Execution process?

Each correct answer represents a complete solution. Choose all that apply.

Select all that apply.

  • A

    Project staff assignments

  • B

    Deliverables

  • C

    Change requests

  • D

    Work performance information