You are planning to add a new site to an existing Connect Plus network. What is the correct sequence in which to perform the logical steps below?
1. Program new frequency file into a number of testing subscriber units.
2. Test the system using testing subscriber units.
3. Configure the new Site Controller.
4. Physically install the RF equipment and IP-Backbone equipment.
5. Update multisite tables at all sites and verify multisite connectivity for the new site.
6. Distribute the new frequency file OTA to the network.
7. Create a new network frequency file.
8. Make any necessary changes based on testing results.
A customer has the following requirement: when the radio user presses the programmed Emergency button on the subscriber, an emergency call will be started. This emergency call will be joined by all users on the same talkgroup at the same site, but it will not propagate to other sites, even if the same talkgroup is registered at other sites.
Can this requirement be met in a Connect Plus system?
You are discussing link bandwidth capacity with a new multisite Connect Plus customer. You explain that certain items, when added to a system, may impact the amount of bandwidth required.
Which of the following places the most additional demand on your network?
You are designing a multisite Connect Plus system with 12 sites. There are 8 repeaters at each site. The customer wants to know how channel priority works. They are concerned about how the system handles multiple transmissions across sites for the same talkgroup call, such as when multiple subscribers at different sites key up simultaneously during hangtime.
Which of the following is the BEST explanation to provide the customer?
NOTE: This is a scenario based item associated with an Oil Corporation. Please reference the information accessible from the "Oil Corporation Scenario" button at the bottom as part of responding to this item.

You are putting together an equipment list for this customer that includes the site controller, subscribers, repeaters, and RF distribution equipment.
Which requirement in the scenario would necessitate an XRT 9000 Gateway?
NOTE: This is a scenario based item associated with an Oil Corporation. Please reference the information
accessible from the "Oil Corporation Scenario" button at the bottom as part of responding to this item.

Given this scenario, which of these customer requirements would require that the customer purchase the XRT 9000 Gateway?
NOTE: This is a scenario based item associated with an Oil Corporation. Please reference the information accessible from the "Oil Corporation Scenario" button at the bottom as part of responding to this item.

In addition to the information in the scenario, what more do you need to know about the customer's IP network to effectively propose a solution?
NOTE: This is a scenario based item associated with an Oil Corporation. Please reference the information accessible from the "Oil Corporation Scenario" button at the bottom as part of responding to this item.

Which of the following are Connect Plus feature(s) and should be specified in order to meet the requirement for maximum availability/redundancy and fault tolerance?
NOTE: This is a scenario based item associated with an Oil Corporation. Please reference the information accessible from the "Oil Corporation Scenario" button at the bottom as part of responding to this item.

In addition to the information in the scenario, which of the following would you also need to know about the customer's Automatic Vehicle Location requirements in determining the most effective design for their Connect Plus system?
NOTE: This is a scenario based item associated with an Oil Corporation. Please reference the information accessible from the "Oil Corporation Scenario" button at the bottom as part of responding to this item.

Which of the following is critical for calculating Connect Plus bandwidth requirements for the site links?