Exit PK0-003 CompTIA Project+
Question 1 of 5
0% complete
Q1 Single choice

Reviewing the results of a control chart, the project manager finds the production samples had results inside both the upper control limit and the lower control limit.

Which of the following is the BEST course of action for the project manager based on this information?

  • A

    The project manager should identify potential new production teams to obtain different results.

  • B

    The project manager should create a report to outline the results for client review and request a more
    generous range between limits.

  • C

    The project manager should stop production until the processes are reviewed in full for identification of flaws.

  • D

    The project manager should continue following the existing process, including the measuring of samples for tracking.

Previous Next