Question 1 of 5
0% complete
Q1 Single choice

In an ongoing project, stakeholders have been approaching team members for status reports and changes without consulting the project manager.

What should the project manager do to ensure a successful project?

  • A

    Send the project charter to all stakeholders for information.

  • B

    Send an email to all stakeholders directing them to approach the project manager directly.

  • C

    Review the stakeholder engagement plan and inform the stakeholders.

  • D

    Review the change management plan and ask the change control board (CCB) to be involved.