Question 1
Single choice

Identify the missing word(s) from the following sentence.
A project is a temporary organization that is created for the purpose of delivering one or more business products according to an agreed?

A.

Senior User

B.

Business Case

C.

Change

D.

Cost

Question 2
Single choice

According to PRINCE2, which of the following is a characteristic of a project compared to that of business operations?

A.

Incurs cost

B.

Introduces business change

C.

Delivers benefits

D.

Creates products

Question 3
Single choice

Which of the following is FALSE?

A.

Manage risks is a PRINCE2 principle

B.

Manage by exception is a PRINCE2 principle

C.

Focus on products is a PRINCE2 principle

D.

Tailor to suit the project environment is a PRINCE2 principle

Question 4
Single choice

According to PRINCE2, which of the following are the aspects of project performance to be managed?

A.

Processes, themes, principles

B.

Time, cost, quality, people

C.

Time, cost, quality

D.

Time, cost, quality, scope, benefits, risk

Question 5
Single choice

What environment does PRINCE2 assume?

A.

Third party

B.

Customer/Supplier

C.

Fixed-price contract

D.

Management and Specialist

Question 6
Single choice

A characteristic of a project is that they come with an element of uncertainty.

Which of the following PRINCE2 themes will help with the identification and management of such uncertainty?

A.

Quality

B.

Risk

C.

Change

D.

Organization

Question 7
Single choice

Which is a benefit of using PRINCE2?

A.

Stakeholders are kept out of planning and decision making

B.

Participants understand each other's roles and needs

C.

Stakeholders are not involved in assuring the project work

D.

All problems are escalated to all stakeholders

Question 8
Single choice

Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?

A.

Continued business justification

B.

Manage by exception

C.

Focus on products

D.

Manage by stages

Question 9
Single choice

Which is NOT a PRINCE2 integrated element?

A.

The principles

B.

The techniques

C.

The themes

D.

Tailoring PRINCE2 to the project environment

Question 10
Single choice

Which is a characteristic of a project?

A.

Are risk free

B.

Have no uncertainty

C.

Are managed as part of business as usual

D.

Are cross-functional