According to SAFe, which of the following metrics are reported at the Inspect and Adapt event?
ART predictability measure
ART cycle velocity
Cumulative value rate
Cumulative value measure
According to the SAFe 6 Scrum Master documentation, one of the metrics that are reported at the Inspect and Adapt event is the ART predictability measure. This metric shows how well the ART delivers on its PI objectives, which are the SMART commitments made by the teams during PI planning. The ART predictability measure is calculated by dividing the total actual business value achieved by the total planned business value, as shown in the PI system demo. The ART predictability measure helps the ART to assess its performance, identify gaps, and improve its forecasting accuracy and reliability. (Must be taken from SAFe 6 Scrum Master resources)
References:
Inspect and Adapt
Program Increment
Exam Study Guide: SSM (6.0) - SAFeScrum Master
What can a Scrum Master/Team Coach recommend to a team that is showing signs of burnout, not addressing increasing technical debt, and acting out of urgency rather than considering innovation?
A constructive IP Iteration at the end of each PI
A collective Iteration Review and demo each Iteration
A communicative retrospective at the end of each Iteration
A careful plan at the beginning of each Iteration
A constructive IP Iteration is one of the recommended practices for Scrum Masters/Team Coaches to help teams avoid burnout, address technical debt, and foster innovation. An IP Iteration is a unique, dedicated iteration that occurs every PI and provides an estimating buffer for meeting PI Objectives and dedicated time for innovation, continuing education, PI Planning, and Inspect and Adapt events. During the IP
Iteration, teams can work on activities such as hackathons, research and design, spikes, refactoring, automation, training, and other improvement initiatives that are difficult to fit into a continuous, incremental value delivery pattern. An IP Iteration also allows teams to prepare for and participate in the PI Planning and Inspect and Adapt events, which are essential for alignment, collaboration, and learning across the ART. A constructive IP Iteration can improve the predictability and flow of value delivery, increase employee engagement and satisfaction, enhance the agility and resilience of the teams, and create a competitive advantage for the enterprise. (Must be taken from SAFe 6 Scrum Master resources)
References:
Innovation and Planning Iteration - Scaled Agile Framework.
The CALMR Approach to DevOps [Complete Guide] - KnowledgeHut SAFe Scrum Master Course Outline
What is one way to ensure a team is holding successful Iteration Reviews and demos?
The team demos working functionality
The team swarms to prepare for demos
The team shares improving metrics
The team ensures they complete every Story
One way to ensure a team is holding successful iteration reviews and demos is to have the team demo working, tested system components that meet the definition of done (DoD). This shows the team's progress and value delivery, and allows them to receive feedback from the product owner and other stakeholders. The team should minimize the use of slides and the preparation time for the demos, and focus on the solution instead of the presentation. The team should also discuss the impact of the current solution on the nonfunctional requirements (NFRs) and identify any risks or impediments.
References:
Iteration Review - Scaled Agile Framework
Exam Study Guide: SSM (6.0) - SAFeScrum Master
During which of the following stages of team development do team members stop focusing on their own goals and begin focusing on developing better ways of working together?
Forming
Norming
Storming
Transforming
Norming is the stage of team development where team members stop focusing on their own goals and begin focusing on developing better ways of working together. Norming occurs after the team has gone through the Forming and Storming stages, where they have established their roles and responsibilities, and have resolved their initial conflicts and disagreements12 In the Norming stage, the team starts to build trust, respect, and cohesion among themselves. They also align on a common vision, mission, and goals, and agree on the norms and expectations for their collaboration and communication 12.
The team becomes more productive, efficient, and effective, as they leverage their collective strengths and skills, and support each other in overcoming challenges and delivering value12 The team also develops a sense of identity and pride, and celebrates their achievements and learnings12 (Must be taken from SAFe 6 Scrum Master resources)
References:
Agile Teams - Scaled Agile Framework
5 Stages of Team Development | Agile Scrum Guide | Book | Blog
What is one way uncommitted objectives help Agile Teams make a plan for the PI?
They ensure the team has additional development options
They generate additional ways to measure team progress
They create an opportunity for teams to take on harder work
They maintain the predictability of achieving the objectives
One way uncommitted objectives help Agile Teams make a plan for the PI is that they maintain the predictability of achieving the objectives. Uncommitted objectives are PI objectives that are not included in the team's commitment or counted against teams in the ART predictability measure. They are used to identify work that can be variable within the scope of a PI, such as stretch goals, spikes, innovation, or exploration1 Uncommitted objectives help improve the predictability of delivering business value since they allow the team to adjust their scope based on the actual progress and feedback during the PI. They also provide the team with some flexibility and capacity to respond to changing needs and expectations, as well as to pursue learning and improvement opportunities12 (Must be taken from SAFe 6 Scrum Master resources)
References:
PI Objectives - Scaled Agile Framework
PI Planning - Scaled Agile Framework
According to SAFe, what is one output of a successful Iteration Retrospective?
Updated ART metrics
Iteration Goals
Improvement Stories
Updated dependencies between Stories
According to SAFe, one output of a successful Iteration Retrospective is the creation of a few improvement Stories that enter the Team Backlog for the next iteration. These stories reflect the team's agreement on what they can do better in terms of their process, practices, and performance. The improvement stories are visible and prioritized along with the other stories in the backlog. They help the team implement the concept of relentless improvement, which is one of the core values of SAFe.
References:
Iteration Retrospective - Scaled Agile Framework, Exam Study Guide: SSM (6.0) -
SAFeScrum Master
What is one way a servant leader can support team members in decision-making?
Give each team member the opportunity to contribute
Perform regular retrospectives on behalf of the team
Identify solutions to problems the team surfaces
Support teams in affinity mapping their concerns
According to the SAFe 6 Scrum Master documentation, one of the ways a servant leader can support team members in decision-making is by giving each team member the opportunity to contribute. This means that the servant leader encourages and facilitates the participation of all team members in the decision-making process, ensuring that everyone's voice is heard and valued. By giving each team member the opportunity to contribute, the servant leader fosters a culture of collaboration, empowerment, and trust, as well as increases the quality and buy-in of the decisions. (Must be taken from SAFe 6 Scrum Master resources)
References:
Scrum Master/Team Coach
The Power of Shared Decision-Making through Servant-Leadership.
The Scrum Master as a Servant-
Leader
Who are important attendees to the PI System Demo?
Board Members
Feature Owners
Business Owners
Portfolio Management
According to the SAFe 6 Scrum Master documentation, one of the important attendees to the PI System Demo is the Business Owners. Business Owners are a small group of stakeholders who have the primary business and technical responsibility for governance, compliance, and return on investment (ROI) for a Solution developed by an Agile Release Train (ART). They are key stakeholders on the ART who must evaluate fitness for use and actively participate in certain ART events. The PI System Demo provides them an opportunity to see the integrated view of new features delivered by the ART, give feedback, and influence the future direction of the solution. (Must be taken from SAFe 6 Scrum Master resources)
References:
System Demo
[Business Owners]
Which of the following events aligns teams on a train?
Architect Sync
Iteration Planning
PI Planning
Coach Sync
PI Planning is one of the events that aligns teams on a train. PI Planning is a cadence-based event for the entire Agile Release Train (ART) that aligns teams and stakeholders to a shared mission and vision. PI
Planning provides an opportunity for the ART to review the business context and priorities, identify and resolve dependencies and risks, and commit to a realistic and achievable plan for the next Program Increment (PI). PI Planning is essential to SAFe: If you are not doing it, you are not doing SAFe1 (Must be taken from SAFe 6 Scrum Master resources)
References:
PI Planning - Scaled Agile Framework
Planning Interval (PI) - Scaled Agile Framework
Preparing for PI Planning | Checklist for Scrum Masters and Product ...
Scrum Master - Scaled Agile Framework
SAFe6.0 Scrum Master Certification (SSM) Course - Vinsys
What is one responsibility of a Scrum Master/Team Coach?
Demoing the system
Testing the system
Improving flow
Prioritizing the backlog
One of the responsibilities of a Scrum Master/Team Coach is to help the team achieve flow, which is a state of continuous and sustainable delivery of value. They do this by teaching and coaching the team on SAFe Scrum and SAFe Team Kanban practices, such as limiting work in progress, visualizing work, managing queues, and reducing batch sizes. They also help identify and eliminate impediments and bottlenecks that hinder the team's progress and performance.
References:
Scrum Master/Team Coach - Scaled Agile Framework Exam Study Guide: SSM (6.0) - SAFeScrum Master