Exit 1Z0-1075-22 Oracle Manufacturing Cloud 2022 Implementation Professional
Question 2 of 5
0% complete
Q2 Single choice

A manufacturing plant works for two shifts of 8 hours each. The Manufacturing user wants a work center resource R1 of 4 units to be available during a nonworking time outside the regular shift on a particular day.
Identify the sequence of steps to create a resource exception in the Manage Work Center Resource Calendar page.

  • A

    Click Outside the existing Shift time on a Specific Date> Create Work Center page> Click the Resource
    Availability tab> Click Add icon> Select R1 from Resource Drop-down list> Enter 4 in Default Units
    Availability column.

  • B

    Click Inside the existing Shift time on a Specific Date> Action Menu> Select Create Resource
    exception> Populate Start and Duration Field> Resource Availability region> Populate 4 units in Default
    Availability column.

  • C

    Click Inside the existing Shift time on a Specific Date>Create Work Center page>Click the Resource
    Availability tab>Click Add icon> Select R1 from Resource Drop-down list> Enter4 in Default Units
    Available.

  • D

    Click Outside the existing Shift time on a Specific Date> Action Menu> Select Create Resource
    exception> Populate Start and Duration Field> Resource Availability and Overrides Region> Populate
    4 units in Availability Override column.