Assume a simple ABC compile was run for the following three items using Current on hand value as the compile criterion.
Item 1 On hand quantity = 20, Frozen Cost = $10 Item 2 On hand quantity = 10, Frozen Cost = $15 Item 3
On hand quantity = 5, Frozen Cost = $50
Select the correct sequence of the items for an ABC class.

  • A

    Item 1, Item 2, Item 3

  • B

    Item 2, Item 3, Item 1

  • C

    Item 1, Item 3, Item 2

  • D

    Item 2, Item 1, Item 3

  • E

    Item 3, Item 1, Item 2

  • F

    Item 3, Item 2, Item 1