Exit 1Z0-902 Oracle Exadata Database Machine X9M Implementation Essentials
Question 2 of 5
0% complete
Q2 Single choice

A new Exadata Quarter Rack with 2 Database Servers and 3 HC Storage Servers and 3- phase 15kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU.

Which statement is correct?

  • A

    The installation can go ahead, no change is required.

  • B

    The installation cannot proceed until two power feeds are available per PDU.

  • C

    A splitter cable can be used to provide power to all PDU cables.

  • D

    The power cables from the servers to the PDUs can be rearranged inside the rack following OECA guidance to utilize a single PDU power cable.