Q1 Single choice

You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.

You have the following requirements:

All work and progress on individual projects must be reflected in the e-commerce portal development program.

Each group must be able to manage their own tasks.

You need to set up the e-commerce portal development program and its associated projects in Microsoft
PPM.

Where should you add resources?

  • A

    in the e-commerce portal development program project site

  • B

    in the individual project schedules

  • C

    in Build Team, in the e-commerce portal development program schedule

  • D

    in the individual project sites