Exit 70-348 Managing Projects and Portfolios with Microsoft PPM
Question 3 of 5
0% complete
Q3 Single choice

You are a project manager for an organization that is using Microsoft Project.

You have enabled Single Entry Mode and team members update their task status using timesheets.

You need to see how these updates impact your project before you approve the tasks.

What should you do?

  • A

    From Project Professional Backstage view, review updates.

  • B

    From Project Professional Tracking Gantt, review updates.

  • C

    From Project Professional Task Usage, review updates.

  • D

    Go to the PWA Approvals page and run the rules you have configured.