Q2
Single choice
You manage a development team by using Microsoft Team Foundation Server (TFS) 2012. The development team is made up of developers with specific skills.
The project you are developing has the following characteristics: Several external dependencies exist.f
Requirements are well defined and will not change.
If an external dependency on the critical path does not meet a committed to deadline, the project will be impacted.
The impact should be identified and measured.
You need to select the appropriate tool(s) for managing the project.
What should you do?