Q2
Single choice
You manage a project by using Microsoft Project.
A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.
You need to implement a solution to meet the stakeholder's request.
What should you do?