Q3
Single choice
You have an active development team (Team A) building enhancements for an application (App X'). and ate currently using the TEST environment for UAT.
A separate operations team ('Team B) discovers a critical error in the Production instance of App X that they must remediate.
However. Team 6 does not have a hotfix stream for which to accomplish this The
available environments are DEV.
TEST, and PROD Which risk mitigation effort should both teams employ to ensure Team AS capital project is only minorly interrupted, and Team B s critical fix can be completed and deployed quickly to end users?