Exit APM-PFQ APM Project Fundamentals Qualification (PFQ)
Question 4 of 5
0% complete
Q4 Single choice

A Cost Breakdown Structure (CBS) shows costs assigned to:

  • A

    individual work packages using the Work Breakdown Structure (WBS).

  • B

    individual deliverables using the Responsibility Assignment Matrix (RAM)

  • C

    individual resources using the Work Breakdown Structure (WBS).

  • D

    individual resources using the Responsibility Assignment Matrix (RAM).