The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule.

This may Impact the program's benefits realization What should the program manager do next?

  • A

    Update the program benefits management plan and risk register

  • B

    Implement the mitigation plan for the identified risk

  • C

    Adjust the program scope to avoid the risk

  • D

    Document the risk and create a mitigation plan