Exit C_ACTIVATE12 SAP Certified Associate - SAP Activate Project Manager
Question 1 of 5
0% complete
Q1 Multiple choice

Which of the following activities support the Realize Phase of a System Conversion journey to SAP
S/4HANA On-Premise Edition?

There are 2 correct answers to this question.

Response:

Select all that apply.

  • A

    Custom code Adjustment planning

  • B

    Data aging configuration

  • C

    Non-production systems migration

  • D

    Value determination

Previous Next