What are valid scenarios in material processing to use parallel change requests? There are 2 correct answers to this question.

Select all that apply.

  • A

    Approval step in which several approvers need to approve the different change requests and the sequence of their approvals is NOT relevant

  • B

    Separate processors in a relevant sequence need to maintain material general data

  • C

    Approval step in which several approvers need to approve the different change requests and the sequence of their approvals is relevant

  • D

    Separate processors in a NOT relevant sequence need to maintain sales and plant data