Exit C_TPLM22_64 SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4
Question 1 of 5
0% complete
Q1 Multiple choice

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.

Select all that apply.

  • A

    A distribution key must be maintained in the work center

  • B

    Scheduling must have been carried

  • C

    The capacity requirements indicator must not be set in the network header

  • D

    A work center must be maintained in the activity