Exit C_TPLM22_64 SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4
Question 1 of 5
0% complete
Q1 Single choice

Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer.

  • A

    Cost object

  • B

    Material view

  • C

    Assignments

  • D

    Network