Exit C_TS422_2021 SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing
Question 1 of 5
0% complete
Q1 Multiple choice

Which of the following processes lead to an entry in the MRP planing file? (Choose 3)

Select all that apply.

  • A

    Change of the material's procurement type

  • B

    Creation of purchasing contract

  • C

    Creation of dependent requirements

  • D

    Creation of sales order

  • E

    Change of the storage bin