Exit C_TS422_2021 SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing
Question 2 of 5
0% complete
Q2 Single choice

How would you define pegging in the context of Advanced Planning?

  • A

    An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements

  • B

    An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements

  • C

    An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run

  • D

    An evaluation to verify if there are material or capacity shortages in the network after the production planning run.