Exit C_TSCM42_66 SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7
Question 5 of 5
0% complete
Q5 Single choice

Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?

  • A

    Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.

  • B

    Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.

  • C

    Assign an appropriate availability checking rule to the material master for the product.

  • D

    Activate the availability check and assign an overall profile in the production scheduling profile.