Exit C_TSCM42_67 SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7
Question 4 of 5
0% complete
Q4 Single choice

In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot).

What could be the reason?

  • A

    There are no planned orders or production orders present.

  • B

    The repetitive manufacturing indicator has been set.

  • C

    There is no valid production version for this material.

  • D

    There are no requirements present.