Q1 Single choice Flag What does it mean when you set a work order task as an upstream task? A The downstream task must be approved before completing an upstream task B The task must be completed before any downstream tasks can be started C The task is dependent on another work order request D The task cannot he started until any upstream tasks have been completed Correct answer