Q1 Single choice

What does it mean when you set a work order task as an upstream task?

  • A

    The downstream task must be approved before completing an upstream task

  • B

    The task must be completed before any downstream tasks can be started

  • C

    The task is dependent on another work order request

  • D

    The task cannot he started until any upstream tasks have been completed