Exit DASM Disciplined Agile Scrum Master (DASM)
Question 2 of 5
0% complete
Q2 Single choice

A team has completed the work in their Aeration backlog earlier than expected.
There is still three days left of the iteration, what should the team do now?

  • A

    Work on non-critical tasks until the product owner can assign them more work.

  • B

    Work with the product owner to pull more work from the product backlog into their iteration backlog.

  • C

    Report the differences in completion time so the next iteration can be planned more efficiently.

  • D

    Wait for the other groups to complete their work prior to doing anything else.