Exit E_ACTAI_2403 SAP Certified Specialist - Project Manager - SAP Activate for Agile Implementation Management
Question 1 of 5
0% complete
Q1 Multiple choice

When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct ans-wers to this que-stion.

Select all that apply.

  • A

    At the end of Realize phase

  • B

    At the end of Prepare phase

  • C

    At the end of Discover phase

  • D

    At the end of Run phase