Exit EX0-006 Management of Value Foundation
Question 3 of 5
0% complete
Q3 Single choice

Which is a benefit of the MoV Study Leader reporting to the Programme Manager?

  • A

    It enables the Programme Manager to pass valuable lessons learned during one project on to other projects

  • B

    It eliminates the need for regular meetings of the Senior MoV Practitioner and Study Leaders

  • C

    It replaces the need to involve the Project Sponsor in MoV Studies who may be busy

  • D

    It enables the Programme Manager to report to the Senior MoV Practitioner and MoV Board on lessons learned