Exit EX0-007 Portfolio, Programme and Project Offices Foundation
Question 2 of 5
0% complete
Q2 Single choice

Which is a factor to consider when sizing a permanent office?

  • A

    Estimate of time taken to deliver each service provided by an office

  • B

    Number of people working on a single programme

  • C

    Amount of money being invested in a single programme

  • D

    Number of templates already produced