Exit EXIN-ASF Agile Scrum Foundation
Question 5 of 5
0% complete
Q5 Single choice

A team selects a Product Backlog Item (PBI) for the Sprint Backlog.

What must a team do to finish the Product Backlog Item it selects?

  • A

    As much as can be done in the Sprint before the deadline.

  • B

    As much as is required to satisfy the definition of 'done'.

  • C

    Analyze, design, program, test and document the PBI.