Q1 Single choice

Both the facility and information technology managers are asked to assign staff to work together on a major project. Halfway through the project, the managers observe that the team is in a win-lose power struggle because of divergent views among team members.

How should the facility and information technology managers initially intervene?

  • A

    Reestablish meeting guidelines

  • B

    Reassign project managers

  • C

    Assign new team members who have similar personalities

  • D

    Assign additional members from each department to foster more problem-solving