Q3 Single choice

Which of the following organizational structures would be considered unorthodox? [1]

  • A

    Developers within the same team unit test each others' code prior to handing over to a separate testing team for system testing

  • B

    Developers and testers are integrated within the same project team, each role focusing on a different level of testing

  • C

    After developers are done unit testing, business analysts alpha test the system before handing over to a separate testing team for system testing

  • D

    DBAs confirm the referential integrity of the database and developers complete their unit testing before handing over to external organization for system testing