Exit JN0-1302 Data Center Design Specialist (JNCDS-DC)
Question 4 of 5
0% complete
Q4 Multiple choice

Your data center design must ensure that no access switch can become a single point of failure.

Which two actions will satisfy this requirement? (Choose two.)

Select all that apply.

  • A

    Use an MC-LAG between two upstream distribution switches and each access switch.

  • B

    Use a LAG between each access switch and a VRRP interface on a distribution switch.

  • C

    Use a LAG between each server and two or more members of a Virtual Chassis.

  • D

    Use an MC-LAG between two access switches and each server.