Q5 Drag & drop

DRAG DROP

A manufacturer uses route operations and job scheduling.

You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.

You need to adjust the efficiency percentage for the conveyor line calendar.

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Drag each option into the matching blank slot.