You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time.

What is the schedule performance index (SPI) for this program?

  • A

    Negative ten percent

  • B

    .75

  • C

    $300,000

  • D

    $225,000