A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule.

Which of the following would the project manager most likely do NEXT?

  • A

    Create a WBS.

  • B

    Determine predecessors and dependencies.

  • C

    Determine the critical path.

  • D

    Prioritize tasks.