Exit PMI-PBA PMI Professional in Business Analysis (PMI-PBA)
Question 5 of 5
0% complete
Q5 Single choice

A company's management team has decided to deploy a new product. However, there is concern that users may not accept a new product that forces them to change existing practices.

The business analyst should:

  • A

    adhere to the project plan to achieve project objectives.

  • B

    clearly communicate project objectives and attempt to defuse tensions.

  • C

    delay the application's deployment until the conflicts have been resolved.

  • D

    voice user concerns to management and recommend that the project be closed.